A. LS.10002^ Lag.7 + i day -> 11-20-03.
B. LS.10002 - Lag.7 - l day -> 11-20-03.
C. LS.10002 + 1 day -> 11-29-03.
D. LS.10002 - 1 day -> 11-27-03.
A. 1001, 2002, 2002, 2003, 3001
B. 1001, 2002, 2003
C. 2001, 2002, 2003, 2007
D. 1001, 2001, 2002, 2003
A. No, the start-to-start and finish-to-finish relationships are backwards.
B. Yes, except the early finish date is not shown.
C. Yes, the duration is 48 days.
D. No, the total float is not shown correctly.
A. Project variables.
B. Consideration of all stakeholders.
C. Value engineering.
D. Interest rate of owner's construction bonds.
A. EF.11001.
B. LS.11001 + 25 days.
C. EF.11001 + 1 day.
D. 02-19-04.
A. The same as a pure-logic diagram.
B. Only calculated using a computer.
C. Logic networks that are drawn to match the calendar.
D. Used to calculate the most probable activity duration.
A. LF.11001 - Dur.11001 -> 01-16-04.
B. LF.10001 + 1 day -> 01-16-04.
C. LF.1001 + DUR.10001 -> 01-14-04.
D. LF.11001 - 27 days + 1 day -> 01-14- 04.
A. Contentious activity.
B. Milestone.
C. Continuous activity.
D. 1-day activity.
A. Activity 9005.
B. Activity 10002.
C. There is no driving activity for Activity 10001 in the backward pass.
D. Activity 11001.
A. 1000.
B. 2003.
C. 1001.
D. 7001.