For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?

Activity C is a

At the end of month one, did the delay to the parking structure foundation delay the project?

Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

If no time extensions are granted and all actual delays are as described above, what will the total float calculation be at the end of the project?

Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

Estimate to complete (ETC) is __________________.

Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT