AACE-PSP試験無料問題集「AACE International Planning & Scheduling Professional (PSP) 認定」

Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?

Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

Estimate to complete (ETC) is __________________.

When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?

Which of the following are NOT considerations or constraints of the planning process for construction scheduling?

The work breakdown structure is used to organize

In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:

Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

The addition of which of the following relationships would cause a logic loop?

Determine the correct formula and date for the late finish for Activity 2002.