AACE-PSP試験無料問題集「AACE International Planning & Scheduling Professional (PSP) 認定」

Determine the correct formula and date for the late finish for Activity 9004.

There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?

Determine the driving activity for Activity 10001.

What problems can a soils engineer deal with on a project?

What method offers the best chance of the schedule being used effectively to implement the project in the field?

During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?

At a minimum, periodic reporting must be done at what interval?

What is the free float for Activity F?

You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

If Activity E's duration changes to 4 months, what is the overall duration of the project.