CCP試験無料問題集「AACE International Certified Cost Professional (CCP) 認定」
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The following is NOT an advantage of the critical path method:
The following is NOT an advantage of the critical path method:
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.
Student will receive scholarship when the GPA is within top 2%. The mean GPA is 2.8 and standard deviation is 0.5.
How high must the GPA be to qualify for the scholarship?
Student will receive scholarship when the GPA is within top 2%. The mean GPA is 2.8 and standard deviation is 0.5.
How high must the GPA be to qualify for the scholarship?
正解:D
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. What is the current cost performance index (CPI)?
9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. What is the current cost performance index (CPI)?
正解:B
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What is the cost index value of copper at the end of Year 2? (rounded to 2 decimal positions)
What is the cost index value of copper at the end of Year 2? (rounded to 2 decimal positions)
正解:B
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)