PSP試験無料問題集「ASIS Physical Security Professional 認定」
Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?
正解:D
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?
正解:B
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)