PSP試験無料問題集「ASIS Physical Security Professional 認定」

Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?

解説: (GoShiken メンバーにのみ表示されます)
What is the free float for Activity F?

解説: (GoShiken メンバーにのみ表示されます)
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?

解説: (GoShiken メンバーにのみ表示されます)
The BEST reason to use multiple calendars is to:

Determine the correct formula and date for the late finish for Activity 2002.

解説: (GoShiken メンバーにのみ表示されます)
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?

解説: (GoShiken メンバーにのみ表示されます)
Time-scaled logic diagrams are

解説: (GoShiken メンバーにのみ表示されます)
Which of the following project planning situations is the most frequent contributor to cost overruns?

解説: (GoShiken メンバーにのみ表示されます)
What is a key first step in developing a critical path method schedule?

解説: (GoShiken メンバーにのみ表示されます)
Which of the following phases does NOT describe the commonly accepted construction life cycle?

解説: (GoShiken メンバーにのみ表示されます)