A stakeholder has identified a potential scheduling conflict on a current project. This conflict may affect the completion date by pushing it out two weeks. The stakeholder wants to document this timeline risk.
Which action should the stakeholder take to log the risk?
Which action should the stakeholder take to log the risk?
正解:B