A procurement manager is preparing a long-term contract with a major supplier. She decides to use the variable pricing arrangement using price indices. The payment terms describe the circumstances and mechanism where the price is allowed to change. In order to successfully manage this type of contract, the buying organisation should have...?
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
A procurement officer decides to approach the supply market regarding a procurement activity that will specify the use of technology that is very new to the market. The procurement officer is taking this step before the formal tender process is started. Is this approach permitted?
正解:D
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
Rochdale Ltd is looking for a new IT system to automate some of its operations. In designing the specification, procurement manager supposes that it should be done solely by the IT department who have deep expertise on this matter. Is procurement manager's opinion appropriate?
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
MWB operates serviced offices in central London. Rock entered a contractual licence with MWB to occupy office space in Marble Arch and had accumulated licence fees in arrears. The original licence agreement contained a 'No Oral Modification' clause that said: 'All variations to this licence must be agreed, set out in writing and signed on behalf of both parties before they take effect'.
After 6 months, Rock director re-negotiated to extend payment period over phone call and MWB credit controller agreed his proposal. Is this agreement considered as an effective variation to the original licence agreement?
After 6 months, Rock director re-negotiated to extend payment period over phone call and MWB credit controller agreed his proposal. Is this agreement considered as an effective variation to the original licence agreement?
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
Sally places a purchase order to the supplier for some components that her company requires. The supplier delivers the goods as she asks, but the quality assurance team finds that these components are defective and unfit for the company's operations. Which document is the ground to decide whether the goods received are fit for purpose?
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)