PK0-004試験無料問題集「CompTIA Project+ Certification 認定」

The project team has identified all the tasks needed to create project deliverables and grouped them into work packages covering all project scope. Which of the following should be done NEXT?

Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?

A company hires a number of interns and assigns them key roles on a project. Which of the following should the project manager MOST likely anticipate?

The PMO is responsible for: (Choose two.)

The project manager needs to motivate the team; however, is an insufficient budget for awards.
Which of the following motivating agents is the MOST appropriate option the project manager can utilize?

During an ad-hoc meeting, the OM notifies the sponsor that while the project is on schedule, material costs have increased and the project is over budget. To save the project, the PM request a material contract with a less expensive vendor. The sponsor approves the change, and project comes in within target tolerances. The company, however, receives numerous stakeholder complaints.
Which of the following is the MOST likely cause of these complaints?

The quarterly financial statement has been released, and portfolios are losing funding for projects. Which of the following options are MOST appropriate to keep the project alive and on schedule? (Choose two.)

A manufacturer is developing a product that will start in one week. The product has a delivery deadline of 90 days.
Which of the following characteristics classifies this as a project?

A project is in the initiation phase. Which of the following tasks will take place during this phase?

A project manager was reprimanded for failing to complete timely status reports and providing mixed messaging about a project's performance.
Which of the following would be responsible for discussing and resolving this issue?

Language barriers will MOST likely influence a PM to:

解説: (GoShiken メンバーにのみ表示されます)
A project manager conducted an audit of project deliverables. During the audit, the project manager identified a deliverable that did not meet quality standards. Which of the following describes who the project manager should notify FIRST?

A project has activities on the critical path that must be completed before other activities can start:
Task A is dependent on Task C before Task D can be completed.
Task A requires Task B to start.
Task B takes twice as long to complete as Task C.
Which of the following is the appropriate ordering of the critical path?