PK0-004試験無料問題集「CompTIA Project+ Certification 認定」

The project manager has had a large number of change requests approved by the project steering committee, but has been given no extra time to deliver the project.
Which of the following schedule compression techniques should be used by the project manager?

A project manager in a function organization is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20% of allocation to a secondary project. This situation limits and jeopardizes the commitment date.
Which of the following should the project manager do NEXT?

An active project has a CPI of 0.92. Which of the following can be determined?

解説: (GoShiken メンバーにのみ表示されます)
Which of the following describes risk mitigation?

Which of the following are the components of a RACI matrix?

A minor change to the baseline schedule is required. This change will be the second minor modification to the schedule. Which of the following is the appropriate version number?

A project team has failed to deliver on changes the project manager outlined on a call two weeks ago. The project team members indicate they did not remember the contents on the call. Which of the following should the project manager do FIRST to improve the level of awareness of changes to the project schedule?

A project sponsor has repeatedly indicated dissatisfaction with the resjits o' several projects being managed by different individuals and consisting of different teams within the organization. Which of the following is the best action for management to take NEXT?

Which of the following metrics are used to determine a project's EAC?

While starting a new project, management is aligning the project to the organization's strategy, assigning limited resources based upon priorities, and optimizing resource deployment between projects.
Which of the following BEST describes these actions?

Joe, a project team member, was hired after a project was already underway, and he is the only team member who does not have an office. Ann, the project manager, is aware of Joe's resentment and the impact he is having on the project environment. Ann decides to give Joe her office and relocates to a shared work space. This is an example of:

A project manager is trying to explain to a stakeholder why projects are progressively elaborated upon. Which of the following is the BEST ?

During a project, there has been a high turnover of resources provided by a third-party vendor. The project team claims the resources are unable to complete tasks in a timely manner. The vendor assures the team that more resources will be provided to complete the project. Which of the following could have caused the issue with the resources?

A sprint retrospective is being conducted. Which of the following is the BEST way to obtain input?

A daily standup Scrum meeting is BEST accomplished in a:

While planning a project, the project team estimates known expenses but also applies a margin of error for unknown expenses. Which of the following is the project team trying to determine?

Tasks A, B, and C have a duration of two days. Task D has a duration of three days, and Task E has duration of four days.
Task A starts on Day 1, and Task B starts on Day 2. Task C starts after Task A.
Tasks D and E start after Task C.
Which of the following is the critical path if Task B starts on Day 3?