PK0-004試験無料問題集「CompTIA Project+ Certification 認定」

Communication on a project is flowing well. Team members are motivated, and they are allowed to make decisions about their work.
Which of the following management styles is the project manager MOST likely using?

A project team is creating a new product, and stakeholders are having a hard time understanding the product.
Which of the following should be sent to the stakeholders?

During a project, there has been a high turnover of resources provided by a third-party vendor. The project team claims the resources are unable to complete tasks in a timely manner. The vendor assures the team that more resources will be provided to complete the project. Which of the following could have caused the issue with the resources?

Which of the following tasks are responsibilities of the project manager role?

In a projectized organization, a project manager has a need for a testing resource. The first place the project manager should look for this resource is:

Many Question: 01s have arisen regarding a newly identified project. Project team members are anxious to know who will be part of the team and what the project will deliver. Which of the following would be the BEST way to provide this information?

A project manager is overseeing an outsourced team of contractors and subcontractors. One month into the project, the project manager realizes tasks are not being completed on time. Subcontractors are not available at the right time.
Which of the following is the NEXT step for the project manager to take to get the project back on track?

During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB.

Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?

A project manager is creating the monthly report for top management. The project manager has collected the information below:
AC = 100
PV = 80
EV = 120
Based on this information, the CPI reflects which of the following about the project?

解説: (GoShiken メンバーにのみ表示されます)
A sprint retrospective is being conducted. Which of the following is the BEST way to obtain input?

A new executive has joined the organization and is considering adding deliverables to the scope. The sponsor agrees with the executive but does not want to change the completion date. Which of the following options would be MOST useful to the project manager to accommodate the new scope without extending the completion date? (Choose two.)

Which of the following risk strategies is represented by the purchase of insurance?

解説: (GoShiken メンバーにのみ表示されます)
Which of the following shows projected project expenditures?

Because a feature was not meeting documented requirements, a project milestone was not achieved as scheduled. Which of the following activities should the project manager perform NEXT?