PK0-004試験無料問題集「CompTIA Project+ Certification 認定」

Before a team can start on a sprint, they will need to:

A project requires that laptops be obtained immediately. The project manager confirms existing laptops, which were used for a previous project, are available, but authorization is required to use them. Which of the following risk response strategies does this represent?

A project is nearing the expected completion date, but it is behind schedule. The project manager has decided to fast-track the resources.
Which of the following impacts will MOST likely occur? (Choose two.)

Which of the following are examples of organizational change? (Choose two.)

Halfway through a project, the project manager is told it needs to be completed four weeks earlier than originally planned. Which ot the following will MOST likely be impacted to accomplish this goal?

Which of the following includes setting governance gates as well as predecessors and dependencies?

The stakeholders for an active project requested a change that could potentially increase the projected budget. Which of the following should the project manager do NEXT?

Which of the following are major characteristics of sprint planning? (Choose two.)

To maintain an active project's progress, the project manager does not acknowledge any opposing input that was provided. Which of the following techniques is this an example of?

During the storming stage of a project team's development, it is common to experience confusion about tasks and responsibilities because:

An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs.
Which of the following actions should the project manager take?

A company recently went through a project requiring new equipment, new software, and retraining of personnel. This is MOST likely a result of:

Which of the following documents is a snapshot in time of a project during the execution phase?

Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?

Ann, a project manager, is working for a new company. On her first project, the assigned project resources do not follow her direction. She is not allowed to authorize contractors because they say she does not have the authority. Which of the following is the MOST likely for what is happening?