PK0-004試験無料問題集「CompTIA Project+ Certification 認定」

A project has been created, and the project team has been identified. Which of the following is the NEXT step?

A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?

解説: (GoShiken メンバーにのみ表示されます)
Which of the following are characteristics of a matrix organization? (Choose three.)

正解:A,E,G 解答を投票する
A daily standup Scrum meeting is BEST accomplished in a:

A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services.
Which of the following documents will the company MOST likely release FIRST?

Which of the following is the BEST time to establish the project cost baseline?

A project manager decides to release a product one month later, knowing marketing studies have shown doing so could require increased manufacturing capacity. Which of the following risk strategies is being employed?

A project manager notices that project status meetings have been going awry. The project manager decides to limit the meetings to only those participants who have input. Which of the following should the project manager use to communicate to stakeholders who will no longer attend the meetings but need to be kept informed?

A key team member found a new job and will be leaving in two weeks. Which of the following should the project manager do FIRST to minimize negative impacts to the project?

A company decides to give a large section of its development project to another firm to manage and complete because that firm has the appropriately skilled resources to execute the work. This approach is referred to as:

A company has completed its annual strategic planning session. As a result, several related projects, which will achieve the company's technological improvement goals, are identified. Which of the following BEST describes these projects?

Joe, a stakeholder, threatens to withdraw from a project that is not going according to his wishes. The president talks to the project manager regarding options for a response to the stakeholder, and they decide the project will move forward as originally planned.
Which of the following risk strategies was used?

Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?

Rather than sending emails to communicate all project information, the project manager:
Makes telephone calls to key stakeholders for urgent information
Sends emails for routine information
Posts on the project intranet site for required but minimally used information Which of the following BEST represents what the project manager is doing?

A project manager is informed that a team member would like to enhance the code with an additional function. Which of the following should the project manager do NEXT?

At the midway point of execution, the project plan calls for a full review of the risk register. To which of the following is the appropriate party to communicate the official results of this review?

The project sponsor wishes to implement a 24/7 solution for the service desk, requiring the establishment of the capability on three different continents. Which of the following factors is MOST likely to influence communication methods across the project?

The client accepts the critical design review.
Which of the following meetings should be held to move to the NEXT step in the project?

A key stakeholder claims to have not received status updates per the agreement. The PM reviews the communications plan and determines the updates were provided as agreed upon. Which of the following should the PM do NEXT to resolve the inconsistency between the communications plan and the stakeholder's expectations?

Which of the following normally would be completed prior to a vendor responding to an RFP?