PK0-004試験無料問題集「CompTIA Project+ Certification 認定」
During an ad-hoc meeting, the OM notifies the sponsor that while the project is on schedule, material costs have increased and the project is over budget. To save the project, the PM request a material contract with a less expensive vendor. The sponsor approves the change, and project comes in within target tolerances. The company, however, receives numerous stakeholder complaints.
Which of the following is the MOST likely cause of these complaints?
Which of the following is the MOST likely cause of these complaints?
正解:B
解答を投票する
A project has activities on the critical path that must be completed before other activities can start:
Task A is dependent on Task C before Task D can be completed.
Task A requires Task B to start.
Task B takes twice as long to complete as Task C.
Which of the following is the appropriate ordering of the critical path?
Task A is dependent on Task C before Task D can be completed.
Task A requires Task B to start.
Task B takes twice as long to complete as Task C.
Which of the following is the appropriate ordering of the critical path?
正解:D
解答を投票する