PK0-004試験無料問題集「CompTIA Project+ Certification 認定」
A project manager notices that project status meetings have been going awry. The project manager decides to limit the meetings to only those participants who have input. Which of the following should the project manager use to communicate to stakeholders who will no longer attend the meetings but need to be kept informed?
正解:D
解答を投票する
Joe, a stakeholder, threatens to withdraw from a project that is not going according to his wishes. The president talks to the project manager regarding options for a response to the stakeholder, and they decide the project will move forward as originally planned.
Which of the following risk strategies was used?
Which of the following risk strategies was used?
正解:D
解答を投票する
Rather than sending emails to communicate all project information, the project manager:
Makes telephone calls to key stakeholders for urgent information
Sends emails for routine information
Posts on the project intranet site for required but minimally used information Which of the following BEST represents what the project manager is doing?
Makes telephone calls to key stakeholders for urgent information
Sends emails for routine information
Posts on the project intranet site for required but minimally used information Which of the following BEST represents what the project manager is doing?
正解:C
解答を投票する
A key stakeholder claims to have not received status updates per the agreement. The PM reviews the communications plan and determines the updates were provided as agreed upon. Which of the following should the PM do NEXT to resolve the inconsistency between the communications plan and the stakeholder's expectations?
正解:B
解答を投票する