PK0-004試験無料問題集「CompTIA Project+ Certification 認定」
During a project, there has been a high turnover of resources provided by a third-party vendor. The project team claims the resources are unable to complete tasks in a timely manner. The vendor assures the team that more resources will be provided to complete the project. Which of the following could have caused the issue with the resources?
正解:D
解答を投票する
A project manager is overseeing an outsourced team of contractors and subcontractors. One month into the project, the project manager realizes tasks are not being completed on time. Subcontractors are not available at the right time.
Which of the following is the NEXT step for the project manager to take to get the project back on track?
Which of the following is the NEXT step for the project manager to take to get the project back on track?
正解:A
解答を投票する
During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB.

Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?

Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?
正解:B
解答を投票する
A new executive has joined the organization and is considering adding deliverables to the scope. The sponsor agrees with the executive but does not want to change the completion date. Which of the following options would be MOST useful to the project manager to accommodate the new scope without extending the completion date? (Choose two.)
正解:C,D
解答を投票する