PK0-004試験無料問題集「CompTIA Project+ Certification 認定」
A project manager in a function organization is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20% of allocation to a secondary project. This situation limits and jeopardizes the commitment date.
Which of the following should the project manager do NEXT?
Which of the following should the project manager do NEXT?
正解:D
解答を投票する
A project team has failed to deliver on changes the project manager outlined on a call two weeks ago. The project team members indicate they did not remember the contents on the call. Which of the following should the project manager do FIRST to improve the level of awareness of changes to the project schedule?
正解:C
解答を投票する
Joe, a project team member, was hired after a project was already underway, and he is the only team member who does not have an office. Ann, the project manager, is aware of Joe's resentment and the impact he is having on the project environment. Ann decides to give Joe her office and relocates to a shared work space. This is an example of:
正解:C
解答を投票する
During a project, there has been a high turnover of resources provided by a third-party vendor. The project team claims the resources are unable to complete tasks in a timely manner. The vendor assures the team that more resources will be provided to complete the project. Which of the following could have caused the issue with the resources?
正解:D
解答を投票する
Tasks A, B, and C have a duration of two days. Task D has a duration of three days, and Task E has duration of four days.
Task A starts on Day 1, and Task B starts on Day 2. Task C starts after Task A.
Tasks D and E start after Task C.
Which of the following is the critical path if Task B starts on Day 3?
Task A starts on Day 1, and Task B starts on Day 2. Task C starts after Task A.
Tasks D and E start after Task C.
Which of the following is the critical path if Task B starts on Day 3?
正解:D
解答を投票する