PK0-005試験無料問題集「CompTIA Project+ Certification 認定」

A project manager is beginning a new project that will include a high number of complex deliverables. Which of the following is the best to use to track deliverables that are yet to be completed?

解説: (GoShiken メンバーにのみ表示されます)
A project manager is assigned an initiative in a highly regulated industry that requires employees to safeguard certain pieces of PII. Which of the following is the best approach for the project manager to keep the information confidential?

解説: (GoShiken メンバーにのみ表示されます)
A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?

解説: (GoShiken メンバーにのみ表示されます)
A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?

解説: (GoShiken メンバーにのみ表示されます)
During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the following data was documented:
Average worked hours
Which of the following describes the result?

解説: (GoShiken メンバーにのみ表示されます)
A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?

A project sponsor requires a system that is capable of providing integrated management of all the business's core functions. Which of the following systems is the project sponsor describing?

解説: (GoShiken メンバーにのみ表示されます)
After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?

A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product. Which of the following charts would BEST prioritize which defects to address?

解説: (GoShiken メンバーにのみ表示されます)
A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

解説: (GoShiken メンバーにのみ表示されます)
Given the following network diagram:
Which of the following is the critical path?

解説: (GoShiken メンバーにのみ表示されます)
SIMULATION
During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.
INSTRUCTIONS
Review the email with the latest updates sent by the project sponsor and respond in the following order:
1. Select the best tool for tracking the server migration progress.
2. Select the new critical path.
3. Select the correct number of engineers required for the server migration phase.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Select the Appropriate Tool:





Select the new critical path.
Option A

Option B

Option C

正解:
See the solution below in explanation
Explanation:
A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

解説: (GoShiken メンバーにのみ表示されます)
A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

解説: (GoShiken メンバーにのみ表示されます)
While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?

解説: (GoShiken メンバーにのみ表示されます)
During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?

解説: (GoShiken メンバーにのみ表示されます)
A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?

解説: (GoShiken メンバーにのみ表示されます)
Which of the following best describes a benefit of the CI/CD process?

解説: (GoShiken メンバーにのみ表示されます)
During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

解説: (GoShiken メンバーにのみ表示されます)