After an SRDF failover operation, production work has been moved to the remote site. A large number of invalid tracks has accumulated. The tracks need to be synchronized back to the R1 volumes.
Which SRDF operation can reduce the re-synchronization time while continuing production work on the remote site?
Which SRDF operation can reduce the re-synchronization time while continuing production work on the remote site?
正解:B