What are the reasons why Fusionlodule500 & FusionModule800 are generally recommended to customers for typical configuration solutions? (Multiple choice)

正解:A,B,C,D 解答を投票する
UPS5000-E 100kVA, the input switch to be selected by the machine, which of the following is the most suitable ?

Generally speaking, the air supply distance of the air duct is shorter than that of the hood air supply.

When creating a camera in NETECO, in addition to obtaining the IP address of the camera, you also need to obtain ().

After the start-up and debugging of the air conditioner, the indoor temperature is in a reasonable state, and the suction pressure is not lower than () can be regarded as reasonable.

What methods does Fusi onllodul e800 air conditioner configuration support?

During the use of the battery, in order to balance the capacity loss caused by the start-up and discharge of the battery, it is necessary to carry out a continuous and long-term constant voltage charging of the battery, which is called ().

The access control management function of the Netco6000 management system only supports one-way card swiping (you need to swipe your card to enter the door, and press the exit button to go out), but do not support two-way card swipe (you need to swipe your card to enter the door and go out).

The UPS5000-E power chess block adopts a fan fault-tolerant design. When two of the fans are damaged, what percentage of the power module can still be loaded?

FusionModule800 has the function of self-starting of civil air conditioners.

On-demand deployment and avoiding over-investment are the only advantages of Mou Aihua's data center.

Traditional UPS. The number of battery cells is not adjustable, the maintenance cost of the battery is high, and the damage of one battery may lead to the replacement of the entire battery pack. The number of battery cells of UPS5000-A is adjustable, then the adjustable range is?

The total current of the battery pack is 1000A, and 3 sets of batteries are configured.
The most economical configuration of the cable from the UPS to the main switch box is?

After the UPS5000-E is installed, what are the key points for the first power-on inspection? (Multiple choice)

正解:A,B,C,D 解答を投票する
The anti-seismic components of UPS5000 are suitable for earthquake-prone areas, and can effectively support cabinets and prevent cabinets from tipping when earthquakes with intensity 9 or below occur.

Which of the following modules are included in the UPS5000-E that can support hot swapping? (Multiple choice)

正解:A,B,C 解答を投票する
( ) marks the fully charged battery, and discharge it to the specified termination power according to certain discharge conditions.

When UPS2000-G-(6-20KVA) is in ECO mode, the battery indicator and bypass indicator are on at the same time.

When there are multiple computer rooms and they are monitored at the same time, the hierarchical deployment of the monitoring system may occur.

The refrigerant cylinder of Huawei air-cooled air conditioner does not need to be placed upside down on the electronic scale when charging refrigerant.