MB-320試験無料問題集「Microsoft Dynamics 365 Supply Chain Management, Manufacturing 認定」

A paint manufacturer is using Process manufacturing. The manufacturer has a quality error. Batches of paint that use the wrong formula have been marked for rework.
The production planner reports they cannot schedule the batch order even though the order has been estimated.
You need to add reservations to the items to be used for the rework order.
What should you do?

A manufacturer uses route operations and job scheduling.
You use a unique calendar for a conveyor line. The company observes a decrease in the number of hours a conveyor line resource is operational due to breakdowns. You must make a temporary change to the number of hours the resource is available.
You need to adjust the efficiency percentage for the conveyor line calendar.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
正解:
You need to configure the system for plastic operations.
Which two parts should be manually reported as finished? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.

解説: (GoShiken メンバーにのみ表示されます)
A vendor plans to supply replacements for a product that they manufactured.
The cost associated with manufacturing most components of the replacement product differ from costs associated with the original product.
You need to plan for the new cost of the item in determining the sales price.
Which costing version explosion mode should you use?

解説: (GoShiken メンバーにのみ表示されます)
A company that makes artisan chocolate is implementing Dynamics 365 Supply Chain Management.
To safeguard the quality of its ingredients, the company limits recipe substitutions of its chocolates.
its top-selling chocolate bar must contain 20 percent sugar. The sugar can be Obtained from either cane or beet sugar depending on supply at the time of production.
The system must be able to automatically substitute the appropriate sugar items when generating production orders to meet the quality level of sugar even when the preferred concentration of cane sugar is out of stock.
You need to configure the system.
Which three components must you configure? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.

正解:C,D,F 解答を投票する
Note: This question is part of series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company produces and distributes seafood to supermarkets. During the manufacturing process, raw seafood is purchased, cleaned, and packaged into various-sized boxes. Each box may have a different weight.
Product is sold by the box and priced by the pound.
You need to ensure that you can perform transactions at the box level and record the net weight of goods shipped to a customer.
Solution: Set up the product with a sales unit measure of pounds and inventory unit measure of box. Set a standard unit conversation for the product from box to pounds.
Does the solution meet the goal?

解説: (GoShiken メンバーにのみ表示されます)
A company produces multiple products that require an installation kit that includes 50 components.
The company does not want to include these 50 components in every Bill of materials (BOM). You have a BOM kit that includes all 50 components, but you do not want it to produce a separate production order.
You need to set up the product BOM for the finished good.
What should you do?

You are the production scheduler for a manufacturing company. You have run the Resource Group Capacity report as shown in the Resource Group 21 Capacity exhibit. (Click the Resource Group 21 Capacity tab).

After reviewing that report, you run Resource Capacity reports as shown in the Resource 2101 and 2102 Capacity exhibits. (Click the 2101 Capacity and 2102 Capacity tabs.)

You run the Gantt chart report as shown in the Gantt exhibit to determine the production orders scheduled on the resources. (Click the Gantt tab.)

You need to determine the method to schedule the production lines.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
NOTE: Each correct selection is worth one point.
正解:
You need to configure the system to track the cost and delivery performance of VendorZ.
Which two actions should you perform? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.

A company sells large batches of chemicals. Item specifications vary from batch to batch.
You must fulfill multiple orders from the same batch of chemicals. If a single batch cannot be reserved, manual reservation must be used. The system must also make reservations based on the earliest batch receipt date.
You need to set up a new chemical item that automatically uses the new batch reservation logic.
Which three settings should you configure? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.

正解:A,C,E 解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
A manufacturing company uses advanced warehouse management functionality for a new warehouse.
After releasing a production order, you observe that the warehouse work for raw material picking was not generated.
You need to go through the warehouse management setup to determine what is missing.
What three setup configurations must you validate? Each correct answer presents part of the solution.
NOTE; Each correct selection is worth one point.

正解:C,D,E 解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
A company implements manufacturing in Dynamics 365 Supply Chain Management.
The company wants to efficiently produce products comprised of different order types.
You need to select the appropriate production plan.
Which production process should you use for the production run?

解説: (GoShiken メンバーにのみ表示されます)
You are the product manager at an orange juice manufacturing company.
For every 1,000 pounds of orange juice, 20 pounds of orange pulp is created which can be sold or reused profitably. The cost is calculated as a weighted average between the quantity of orange juice that is reported as finished and the orange pulp based on the standard cost of each item.
You need to create the formula for orange juice that will produce orange pulp as a result of finishing a batch order.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
正解:

1 - Create a new formula and formula version for orange juice
2 - Set Total cost allocation on the header to true
3 - Add a by-product line for orange pulp and enter a quantity of 20 pounds per 1,000 pounds
4 - Select Per quantity as the by-product cost allocation
You need to enable the features and configuration keys for the firepits.
Which two features should you enable? Each answer presents part of the solution.
NOTE: Each correct selection is worth one point

A company implements Dynamics 365 for Finance and Operations.
You run a master plan each week.
You need to resolve the issue in the scenario.
What should you do? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.
正解:

Reference:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/job-scheduling
Note: This question is part of series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 Supply Chain Management and configures the system to support process manufacturing.
The company manufactures pain-relieving lotions. Several of the primary ingredients are delivered at different concentrations depending on the ingredient and vendor. IngredientA is the primary active ingredient in the lotion. IngredientB is used as a compensating ingredient.
You need to ensure that the system is set up to support the manufacturing process.
Solution: Create a formula version for each concentration level.
Does the solution meet the goal?

解説: (GoShiken メンバーにのみ表示されます)