CAPM試験無料問題集「PMI Certified Associate in Project Management (CAPM) 認定」
The project manager is looking at a precedence diagram.... the duration of this task?
The project manager is looking at a precedence diagram and needs to report back about the project status The total duration of the task is ten days, and both Activity A and B need be completed. Activity A has a duration of six days, and activity B has a duration of four days Activity B has a finish-to-start relationship with activity A Under current circumstances, activity A will take about seven days to complete.
What is the outcome of the duration of this task'?
The project manager is looking at a precedence diagram and needs to report back about the project status The total duration of the task is ten days, and both Activity A and B need be completed. Activity A has a duration of six days, and activity B has a duration of four days Activity B has a finish-to-start relationship with activity A Under current circumstances, activity A will take about seven days to complete.
What is the outcome of the duration of this task'?
正解:A
解答を投票する