An organization strives hard to accelerate value delivery by improving product design, development, and transition activities. What ways of working should the organization discontinue to become an effective player?

解説: (GoShiken メンバーにのみ表示されます)
An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?

Following a successful product release, senior management asks an agile team how to improve the value of the product for the next release. What should the team do?

An agile project leader is delivering a team kick-off session. The first exercise is a "Life Timeline" - a story- telling exercise where each team member tells their life story, explains how they experienced the highs and lows of their journey, and identifies their fears and hopes.
What is the project leader trying to create?

A project team has a senior subject matter expert (SME) who is comfortable with data integration. The SME is not inclined to perform regression testing because the SME feels that performing regression testing is more of a junior duty.
What should the scrum master do?

An agile team provides feedback that user stories include insufficient details to understand the requirements.
What should the agile practitioner do?

During sprints, the development team members are frequently invited to various meetings to provide technical opinions, consuming the team's working time and causing compliance issues. Which action should the scrum master take to address this situation?

解説: (GoShiken メンバーにのみ表示されます)
During a retrospective meeting, a team develops a large list of initiatives All will have a positive impact and improve team performance What should the agile coach do next?

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope Unless this change is accepted, there is no value to the customers during this iteration.
What must the agile practitioner do?

During backlog refinement meeting, the new developer on the team asks the product owner to discuss a new performance threshold requirement and how it impacts the stories in the backlog. What should the team do?

An agile team often fails to deliver its sprint goal. At a sprint retrospective, the more experienced team members complain that the less experienced team members are working too slowly. This creates tension in the team.
What should the scrum master do to remove this tension?

解説: (GoShiken メンバーにのみ表示されます)
A client needs to release their product to market earlier than planned. They need to start receiving the expected revenue, according to their financial forecast, which will require completing the work left on all user stories in the backlog.
What should the project lead do to accommodate this request?