Which TWO are objectives of the 'controlling a stage process?
1. To focus attention on achieving Work Within) the agree tolerances
2. To create follow on action recommendations for all open issues and risks
3. To understand how the quality required will be achieved
4. To ensure that the stage's products meet-agreed quality expectations
1. To focus attention on achieving Work Within) the agree tolerances
2. To create follow on action recommendations for all open issues and risks
3. To understand how the quality required will be achieved
4. To ensure that the stage's products meet-agreed quality expectations
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
Which of the following statements about the Closing a Project process are true?
1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.
1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.
正解:B