The maintenance engineer creates a single cycle plan with the following parameters:
The call object is maintenance order
The indicator for separate completion of maintenance call date is NOT set The indicator for completion requirement is NOT activated Both shift factors are set to 100% Which date is relevant for the calculation of further planned dates for call objects?
Response:
The call object is maintenance order
The indicator for separate completion of maintenance call date is NOT set The indicator for completion requirement is NOT activated Both shift factors are set to 100% Which date is relevant for the calculation of further planned dates for call objects?
Response: