Universal Containers has a stable continuous integration process and all stakeholders are happy. However, user testing takes longtime, as data has to be setup. What should an Architect do to address this problem?

解説: (GoShiken メンバーにのみ表示されます)
Universal Containers (UC) is midway through a large enterprise project. UC is working in an agile model, and currently has four-week iterations, with a branching strategy supporting this approach. UC operates in a strict regulatory environment, and has dedicated teams for security, QA, and release management. The system is live with users, and a serious production issue is identified at the start of a sprint, which is narrowed down to a bug in some Apex code.
Which three approaches should an architect recommend to address this bug?
Choose 3 answers

正解:A,B,D 解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
Universal Containers (UC) development team is using an Agile tool to track the status of build items, but only in terms of stages. UC is not able to track any effort estimates, log any hours worked, or keep track of remaining effort. For what reasons should UC consider using the agile tool for effort tracking?

解説: (GoShiken メンバーにのみ表示されます)
Universal Containers (UC) has a customized repository that represents lots of different apps or projects. UC currently is trying to shift from the org development model to the package development model to manage changes. In the org development model, each developer starts their work within their own personal sandbox.
When it comes to choosing development environments, what should a Salesforce architect recommend?

解説: (GoShiken メンバーにのみ表示されます)
What are the three considerations that the architect should recommend for Change Set deployment?
Choose 3 answers

正解:C,D,E 解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
Which two ways should a developer working on a data loading integration that operates between different Salesforce environments insert multiple related records in one call or transaction?
Choose 2 answers

解説: (GoShiken メンバーにのみ表示されます)
When replacing an old legacy system with Salesforce, which two strategies should the plan consider to mitigate the risks associated with migrating data from the legacy system to Salesforec? Choose 2 answers?

解説: (GoShiken メンバーにのみ表示されます)
The team at Universal Containers is building an application on Java that will interact with its Salesforce application. They want to use SOQL queries to retrieve and make changes to smaller pieces of Salesforce metadata through this application.
Which API should the team leverage?

解説: (GoShiken メンバーにのみ表示されます)
Northern Trail Outfitters (NTO) has well-defined release management processes for both large and small projects. NTO's development team created a workflow and a trigger for the changes in its opportunity renewal process.
What should the architect recommend for release planning of these changes?

解説: (GoShiken メンバーにのみ表示されます)
Universal Containers CUC) is considering implementing a minor change policy for a series of low-risk user stories that are commonly received by the UC admins. The policy would allow admins to make these changes directly in production. UC does not have continuous integration/continuous delivery (CI/CD) in place.
Which three best practices should the architect suggest UC follow for their new change policy? Choose 3 answers

正解:A,C,D 解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
Which two decisions should be made by an Architecture Review Board (ARB)? Choose 2 answers

解説: (GoShiken メンバーにのみ表示されます)
Universal Containers has multiple project teams integrating Salesforce to various systems Integration Architects are complaining about the various integration patterns used by the teams and lack a common understanding of the integration landscape. What should architect recommended to address the challenges?

解説: (GoShiken メンバーにのみ表示されます)
Which two statements are accurate about why Mock objects are needed when writing test classes?
Choose 2 answers

解説: (GoShiken メンバーにのみ表示されます)
Universal Containers (UC) has multiple development teams that work on separate streams of work, with different timelines. Each stream has different releases of code and config, and thedelivery dates differ between them.
What is a suitable branching policy to recommend?

解説: (GoShiken メンバーにのみ表示されます)
Universal Containers is having trouble deploying metadata from SIT to UAT. UAT is complaining that it does not recognize some new Salesforce metadata types to be deployed. The deployment from Dev to SIT worked perfectly What could be the problem?

解説: (GoShiken メンバーにのみ表示されます)
Universal Containers has several concurrent projects building new functionality, fixing bugs, and modifying existing functionality. Management would like features to be available to users as quickly as possible, even if the entire project is incomplete. What should an Architect recommend to maintain quality?

解説: (GoShiken メンバーにのみ表示されます)