LEED-AP-BD-C試験無料問題集「USGBC LEED AP Building Design + Construction (LEED AP BD+C) 認定」
When measuring sound pressure levels in a classroom to determine compliance with the HVAC background noise requirements of LEED Building Design and Construction: Schools, Indoor Environmental Quality Prerequisite, Minimum Acoustic Performance, what testing conditions are appropriate for the classroom?
正解:D
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
A LEED Building Design and Construction: New Construction office building's HVAC system includes hot water from a central utility plant. The central utility plant is owned and operated by a management company.
The office pays a flat fee for hot water, included as part of the lease. The management company does not meter or invoice for actual hot water consumption. For the project to meet the requirements for Energy and Atmosphere Prerequisite, Building-Level Energy Metering, an energy meter must be installed for
The office pays a flat fee for hot water, included as part of the lease. The management company does not meter or invoice for actual hot water consumption. For the project to meet the requirements for Energy and Atmosphere Prerequisite, Building-Level Energy Metering, an energy meter must be installed for
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
During the early stages of a LEED for Schools project, the team was able to reduce the number of lighting fixtures in classrooms by 25% because the project team selected paint color whose light reflectance value was
75% instead of the initially proposed 64% value. This strategy is an example of applying which of the following credits to the project?
75% instead of the initially proposed 64% value. This strategy is an example of applying which of the following credits to the project?
正解:D
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
A new commercial building is being designed to use small capacity air handling units. To meet the requirements of the Carbon Dioxide Monitoring strategy in the Indoor Environmental Quality Credit, Enhanced Indoor Environmental Quality Strategies, where would CO2 monitors need to be located?
正解:D
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
The required minimum scope of analysis for a product-specific declaration that contributes toward Materials and Resources Credit, Building Product Disclosure and Optimization - Environmental Product Declarations, Option 1. Environmental Product Declaration is
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
A topographic assessment of a project site located 150 ft. (45 m) from a water body was conducted. The results of the slope analysis show that the site is generally sloping 6% to 8% to the northwest over most of the site, with some steep slopes located at the eastern edge of the property, which may impact the runoff volume.
Which one of the following LEED credits or prerequisites will be affected by these results?
Which one of the following LEED credits or prerequisites will be affected by these results?
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
A project has total waste of 20 tons (18.1 tonnes) that includes the following:
8 tons (7.3 tonnes) of recycled demolition steel and concrete
2 tons (1.8 tonnes) of trees cleared from the site
. 3 tons (2.7 tonnes) of commingled scrap with 40% diverted
. 6 tons (5.4 tonnes) of used furniture donated to a non-profit organization
1 ton (0.9 tonnes) of removed carpet and ceiling tiles sent back to the manufacturer What is the percentage of diverted waste for Materials and Resources Credit, Construction and Demolition Waste Management?
8 tons (7.3 tonnes) of recycled demolition steel and concrete
2 tons (1.8 tonnes) of trees cleared from the site
. 3 tons (2.7 tonnes) of commingled scrap with 40% diverted
. 6 tons (5.4 tonnes) of used furniture donated to a non-profit organization
1 ton (0.9 tonnes) of removed carpet and ceiling tiles sent back to the manufacturer What is the percentage of diverted waste for Materials and Resources Credit, Construction and Demolition Waste Management?
正解:B
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)